Image
The rafters were in place with only a few weeks before the bad weather set in for good.
The process of bringing each rafter to a level position (each rafter touches three different logs... uneven logs, I might add) working 36 feet in the air on icy ladder rungs was daunting. 
In good weather Brian was able to level four sets of rafters (eight individual rafters). This slowed down to two sets in an 8 hour day when it got icy.

Currently, half of the 26 sets of rafters are leveled and strapped. 
Our hope of getting the roof on before winter just wasn’t meant to be. So we are trusting that come spring, work will continue, and praying for only minimal damage to the exposed rafters. 
It has been quite stressful to leave the house in this condition over the winter. Likely one or two more weeks of good weather and we would have gotten the sheeting on.
Lesson learned….work hard in the spring if at all possible (we were waiting on equipment) and leave plenty of room to finish project before fall…